Metsamor NPP to undergo maintenance
Armenia's nuclear power plant in Metsamor will temporarily stop its operation from September 15 to undergo regular maintenance, Director of the Metsamor NPP Gagik Markosyan told A1+.
The maintenance work will continue for 88 days.
"The plant undergoes general overhaul every four years. This year we are going to fix the reactor," he said.
The NPP will resume its operation on December 12.